Zimbabwe Chrome Beneficiation & Wash Plant Dashboard

Currency
US$1 = ₹95.1906

Technical, commercial and regulatory screening for a modular chrome wash and gravity-concentration plant in Zimbabwe. All values are preliminary screening assumptions, not vendor quotations or a bankable feasibility study.

1. Executive Investment View

Proceed to validation and pre-FEED; do not move directly to EPC.
Installed CAPEX
Indicative first commercial module
Processing OPEX
Per tonne of ROM
Contained Recovery
72%
Base case; range 55%–85%
Mass Yield
45.8%
At 28% feed and 44% concentrate

Decision Summary

Conditional

Technically feasible Commercially unproven

A complete wash and gravity-concentration plant is feasible for suitable ore. Approval depends on representative testwork, water security, a domestic smelter or toll-smelting route, and written product-specific regulatory confirmation.

Recommended Business Model

Mine-controlled or contracted ore → 50 TPH modular wash plant → verified concentrate quality → domestic smelter sale or toll smelting → expansion to 100 TPH after stable operating proof.

2. Project Basis

Operating Hours
16 h/day
300 operating days/year
Annual ROM
240,000 t/y
Range 108,000–600,000 t/y
Head Grade
28% Cr₂O₃
Range 18%–40%
Concentrate Output
≈110,000 t/y
Ore-specific

Base Parameters

ParameterBaseRange / note
Throughput50 TPH30–100 TPH
Recovery72%55%–85%
Concentrate grade44% Cr₂O₃40%–48%
Project life10 years minimum7–15+ years

Core Feasibility Question

Can a specific ore produce a consistent, smelter-acceptable concentrate at sufficient recovery and margin after mining, transport, water, tailings, power, statutory charges and working capital?

Do not purchase a standard plant package from a throughput brochure alone.

3. Metallurgical Testwork Programme

Mandatory before final equipment selection.
TestPurposeMinimum output
Representative samplingCapture seam, pit, depth and supplier variabilityComposite plan and chain of custody
Chemical assayMeasure Cr₂O₃, Fe, SiO₂, Al₂O₃, MgO, P and SHead, fractions, products and tails
Mineralogy / QEMSCAN / MLAIdentify locking and liberationMineral associations by size
Scrubbing and sizingMeasure clay removal and fines generationWater demand and retention basis
Jig / DMSAssess coarse pre-concentrationCoarse yield and grade
Spiral rougher-cleaner-scavengerDevelop main fines circuitGrade-recovery curve
Fine recovery / magnetic separationAssess ultrafines and Cr/Fe improvementIncremental recovery versus cost
Settling and dewateringSize thickener, pumps and filtrationSettling rate and product moisture

4. Recommended 50 TPH Process Design

1. ROM ReceivingHopper, grizzly and controlled feeder
2. Size ReductionJaw crusher or sizer
3. ScrubbingRotary scrubber or log washer
4. ScreeningTrommel and multi-deck screens
5. Coarse RecoveryJig or DMS if justified
6. ClassificationHydrocyclones and sumps
7. Rougher SpiralsPrimary gravity recovery
8. Cleaner/ScavengerBalance grade and recovery
9. Fine RecoveryTables, MGS or magnetic separation
10. DewateringScreen, thickener or filter
11. Water ReturnThickener and return-water dam
12. Product HandlingStockpile, sampling and weighbridge

5. Base-Case Mass Balance & Product Quality

Illustrative Annual Mass Balance

StreamTonnes/yearCr₂O₃ grade
ROM feed240,00028.0%
Concentrate109,96444.0%
Tailings / rejects130,03614.5%

Commercial Product Targets

ParameterTargetImportance
Cr₂O₃40%–48%Contained chrome
Cr/Fe ratioOften >1.5Furnace economics
SiO₂As low as practicalSlag and power
P and SLow and controlledBuyer acceptance
MoistureBelow agreed maximumTransport and stability
VariabilityNarrow batch rangePricing and burden control

6. Plant Sizing Alternatives

Installed CAPEX by Plant Size

Scale Comparison

SizeAnnual ROMInstalled CAPEXBest use
30 TPH108,000–144,000 t/yPilot-commercial
50 TPH180,000–300,000 t/yRecommended first module
100 TPH360,000–600,000 t/yMulti-mine hub
200 TPH720,000–1.2M t/yLarge integrated producer
Recommendation: Start with 50 TPH and size shared infrastructure for a second module.

7. CAPEX Estimate

Low
Installed plant
Base
Conservative planning basis
High
Higher infrastructure case
Decision Rule
Pre-FEED first
Competitive bids and contingency

Base CAPEX Breakdown

Low / Base / High

8. Processing OPEX

Low
Per tonne ROM
Base
Per tonne ROM
High
Per tonne ROM
Largest Drivers
Wear + Power
Ore variability and water recycle matter

Base OPEX Breakdown

OPEX Range

9. Water, Tailings, Power & Staffing

Process Circulation
120–250 m³/h
High recycle
Fresh Make-up
10–35 m³/h
≈50,000–170,000 m³/y
Connected Load
350–800 kW
Average 250–600 kW
Employment
35–65
Direct jobs

Tailings Options

OptionAdvantageConstraint
Wet TSFSimpleWater loss and footprint
Thickened tailingsBetter water recoveryPumping complexity
Dry stackMaximum water recoveryHigh CAPEX
In-pit / co-disposalLower footprintMine-plan integration

Operating Model

  • Two 8-hour shifts plus maintenance.
  • Backup generation for pumps and safe shutdown.
  • Weekly and monthly planned maintenance.
  • Batch laboratory control and umpire assays.
  • Critical spares for pumps, screens and spirals.

10. Commercial Sensitivity

Downside / Base / Upside

VariableDownsideBaseUpside
Head grade22%28%34%
Recovery60%72%82%
Concentrate grade42%44%46%
Utilisation55%75%88%

Management Sensitivities

SensitivityApproximate effect
5 percentage-point utilisation change≈16,000 t/y ROM
5 percentage-point recovery changeLarge impact on concentrate tonnes
Obtain a binding term sheet covering specification, sampling, pricing, penalties, transport, payment security and off-spec treatment.

11. Regulatory & Compliance Pathway

Mining Title

Verify authority to mine and process owned or third-party ore.

Legal gate

Beneficiation Approval

Obtain written approval for the exact plant and product scope.

Product-specific

ESIA & Effluent

Complete environmental and effluent licensing.

Before implementation

Water Allocation

Secure ZINWA or Catchment Council agreement.

Critical path

MMCZ Registration

Register production, sales and sampling controls.

Commercial prerequisite

Custody & Weighing

Use auditable weighbridge, sampling and stock controls.

Control system
Regulatory warning: A wash plant does not automatically create a right to export concentrate. Obtain a current written Ministry/MMCZ position before committing capital.

12. Implementation Schedule

StageTimingMain workGate
Ore and title screenMonth 0–2Sampling, title, logistics, buyer discussionsRepresentative feed and clean rights
Laboratory testworkMonth 2–4Mineralogy, sizing and gravity testsTarget grade and recovery
Pilot qualificationMonth 4–6Bulk sample and buyer testingAccepted product and mass balance
Pre-FEEDMonth 5–8Layout, water, tailings, power and civilsNo fatal flaw
Permits & contractsMonth 6–10ESIA, water, Ministry/MMCZ and offtakeWritten approvals and binding route
Tender & financingMonth 8–11Competitive bids and financingCAPEX approved
ConstructionMonth 11–17Civils, erection and commissioningPerformance test
Ramp-upMonth 17–20Campaign control and optimizationThree stable months

13. Final Recommendation

Proceed Now

Approve a six-month validation phase: sampling, mineralogy, pilot gravity testwork, buyer qualification, water/tailings studies and a product-specific regulatory opinion.

Do Not Approve Yet

Do not approve EPC until buyer specification, economic recovery, water, permits, offtake and funding are secured.