Spodumene Concentration Plant Dashboard

Beneficiation and concentration dashboard for a Zimbabwe lithium project designed to produce 5.5%–6.0% Li₂O spodumene concentrate as feed for a lithium sulphate plant. This dashboard sits between mine validation and lithium sulphate refining.

1. Executive Summary

Indicative assumptions. Replace with metallurgical testwork, vendor quotes, and mine feed data.

Purpose

This plant upgrades mined lithium ore into saleable or internally usable spodumene concentrate. The target is to produce consistent 5.5%–6.0% Li₂O concentrate for downstream lithium sulphate production.

Current View: Conditional

Strategic Role

The concentration plant is the bridge between the mine and the chemical plant. If this stage fails to produce quality concentrate, the lithium sulphate plant economics collapse.

Critical Question

Can the ore be upgraded to 6% Li₂O concentrate at 70%+ recovery, with acceptable impurities, water use, tailings handling, and operating cost?

No sulphate EPC before beneficiation validation

Investment gate: the lithium sulphate plant should not proceed until this concentration stage proves stable concentrate quality, recovery, mass yield, impurity control, and plant-feed continuity.

2. Project Snapshot

Base-case concentration plant assumptions.
Concentration Plant Capex
$15M
Base case within $10M–20M range
Ore Feed
174 ktpa
Assumes 1.2% Li₂O ore
Concentrate Output
25 ktpa
Feed for sulphate plant
Concentrate Grade
6.0%
Li₂O target grade
Recovery
72%
Base-case beneficiation recovery
Mass Yield
14.4%
Concentrate / ore feed
Processing Cost
$38/t ore
Indicative beneficiation opex
Validation Status
Pending
Requires pilot testwork

3. Process Route

Typical hard-rock spodumene beneficiation route.

Beneficiation Flow

ROM Ore Primary Crushing Secondary Crushing Screening Ore Sorting / DMS Optional Grinding Desliming Flotation Thickening Filtration 6% Spodumene Concentrate Lithium Sulphate Plant Feed

Route A: DMS-Heavy

Best if ore has coarse spodumene liberation. Lower reagent use and lower grinding cost, but may not recover fine spodumene.

Lower opex if ore is suitable

Route B: Flotation-Heavy

Better for fine-grained or complex ore. More flexible but higher reagent, water, and tailings complexity.

Higher process control required

Route C: DMS + Flotation

Often the most balanced option: DMS recovers coarse spodumene and flotation treats fines or middlings.

Recommended base-case route

4. Indicative Mass Balance

Base case: 1.2% Li₂O ore, 6% Li₂O concentrate, 72% recovery.

Mass Balance Chart

Mass Balance Table

ParameterValueComment
Annual ore feed174,000 tonnesRequired to produce 25 ktpa concentrate at base assumptions
Ore grade1.2% Li₂OPreferred minimum for this project
Contained Li₂O in ore2,088 tonnesOre feed × grade
Beneficiation recovery72%Requires testwork confirmation
Recovered Li₂O1,503 tonnesContained Li₂O × recovery
Concentrate grade6.0% Li₂OTarget feed quality for sulphate plant
Concentrate output~25,000 tonnes/yearBase case target
Tailings / rejects~149,000 tonnes/yearRequires tailings and water management

5. Capex Cost Breakdown

Indicative small commercial concentration plant capex.

Capex Breakdown Chart

Cost Breakdown Table

SectionLowBaseHigh
ROM pad, feed hopper, conveyors$0.5M$1.0M$1.8M
Primary and secondary crushing$1.2M$2.2M$3.5M
Screening and classification$0.5M$1.0M$1.8M
Ore sorting / DMS module$1.5M$3.0M$5.0M
Grinding circuit$1.2M$2.5M$4.0M
Desliming and conditioning$0.4M$0.9M$1.5M
Flotation circuit$1.5M$3.0M$5.5M
Thickening, filtration, concentrate handling$1.0M$2.0M$3.5M
Tailings and water circuit$0.8M$1.8M$3.2M
Power, utilities, lab, automation$1.0M$2.0M$3.5M
Civil works, EPCM, commissioning, contingency$2.0M$3.6M$6.7M
Total Estimated Cost$11.6M$23.0M$40.0M

Note: The project KPI uses a USD 15M optimized base-case target. The detailed line-item table shows a broader scope envelope before vendor quotes, infrastructure exclusions, and process-route optimization.

6. Major Equipment Required

Equipment list for a DMS + flotation spodumene concentration plant.
AreaMain EquipmentIndicative CostImportance
ROM handling ROM pad, grizzly, feed hopper, apron feeder, belt conveyors $0.5M–1.8M Medium
Crushing Jaw crusher, cone crusher, VSI if required, magnets, dust suppression $1.2M–3.5M Critical
Screening Vibrating screens, classification screens, oversize return conveyors $0.5M–1.8M High
Ore sorting / DMS Sensor sorter if used, dense media cyclones, DMS screens, medium recovery system $1.5M–5.0M High
Grinding Ball mill or rod mill, hydrocyclones, slurry pumps $1.2M–4.0M Critical
Desliming Hydrocyclones, attrition scrubbers, conditioning tanks $0.4M–1.5M High
Flotation Rougher, cleaner, scavenger flotation cells, reagent dosing skids $1.5M–5.5M Critical
Dewatering Concentrate thickener, filter press, concentrate dryer if required $1.0M–3.5M High
Tailings Tailings thickener, pumps, tailings storage, water return system $0.8M–3.2M Critical
Utilities and control MCC, switchgear, PLC/SCADA, lab, water system, compressed air $1.0M–3.5M High

7. Operating Cost Analysis

Indicative beneficiation operating cost before mine mining cost and chemical refining cost.

Opex Cost Stack

Opex Table

Cost ItemIndicative CostComment
Power$8/t oreCrushing, grinding, pumps, flotation
Reagents$7/t oreCollectors, frothers, pH modifiers, flocculants
Labour$6/t oreOperators, supervisors, lab, maintenance
Maintenance$6/t oreWear liners, pumps, mills, screens
Water and tailings$4/t oreWater recovery, tailings pumping, compliance
Consumables$3/t oreGrinding media, filter cloth, lubricants
G&A and lab testing$4/t oreAdmin, sampling, assay, QA/QC
Total Beneficiation Opex$38/t oreBase-case assumption

Cost per Tonne Concentrate

MetricValue
Annual ore feed174,000 tpa
Beneficiation opex$38/t ore
Annual beneficiation cost$6.61M
Annual concentrate production25,000 tpa
Beneficiation cost per tonne concentrate~$264/t concentrate

Integrated Feed Cost Warning

The lithium sulphate plant economics should not use beneficiation cost alone. It should include mining cost, beneficiation cost, site logistics, concentrate handling, sustaining capex, and working capital.

Use full concentrate transfer cost in sulphate ROI model

8. Concentrate Quality and Plant-Feed Requirements

These specifications must be confirmed with the lithium sulphate plant process vendor and buyer.

Concentrate Specification

ParameterTargetStatus
Li₂O grade5.5%–6.0%Test Required
Recovery70%+ preferredTest Required
Moisture<8%Process dependent
Particle sizeSuitable for calcination feedVendor confirmation
IronLow / vendor specificationTest Required
MicaLowFlotation risk
FluorineLowProcess and ESG risk
ConsistencyStable monthly gradeRequired

Quality Risk Score

Impurity Watchlist

Impurity / IssueWhy It MattersRisk
Iron mineralsCan affect downstream sulphate product qualityHigh
MicaCan consume reagents and reduce concentrate gradeHigh
Fine slimesCan reduce flotation recoveryHigh
High feldspar/quartz dilutionCan lower concentrate gradeMedium
Variable ore zonesCan create unstable plant feedHigh
MoistureAffects handling, transport, and calcinationMedium

Required Testwork

TestPurposePass Criteria
Mineralogy / liberation studyConfirm liberation size and gangue mineralsClear concentration route
DMS testEvaluate coarse pre-concentrationEconomic recovery and grade uplift
Flotation testProduce 5.5%–6% concentrate70%+ recovery preferred
Locked-cycle flotationSimulate continuous operationStable grade and recovery
Thickening and filtration testConfirm dewatering performanceMoisture target achieved
Concentrate calcination testConfirm downstream sulphate feed suitabilityGood conversion and leachability

9. ROI Impact and Sensitivity

Concentration performance flows directly into lithium sulphate plant economics.

Recovery Impact on Concentrate Output

Grade and Recovery Matrix

Ore Grade / Recovery60%72%82%
0.8% Li₂OToo WeakHigh RiskPossible
1.0% Li₂OHigh RiskConditionalGood
1.2% Li₂OConditionalPreferredStrong
1.5% Li₂OGoodStrongExcellent

Impact on Lithium Sulphate Plant

Concentration OutcomeEffect on Sulphate Plant
6% concentrate, 72%+ recoveryBase-case sulphate economics supported
5.5% concentrate, 65% recoveryLower throughput or higher feed cost
<5.5% concentrateSulphate plant may need redesign or reject feed
High iron / mica / fluorineHigher purification cost and buyer risk
Unstable monthly concentrate qualityChemical plant uptime and product quality risk

Concentration Plant Viability Score

64 / 100

Pending Beneficiation Testwork

Score can improve after DMS/flotation tests prove 6% concentrate, 70%+ recovery, manageable impurities, reasonable opex, and stable dewatering.

10. Risk Register

Key concentration-stage risks before committing to downstream chemical plant.
RiskDescriptionRatingMitigation
Recovery riskPlant may not recover enough lithium into concentrate.CriticalDMS/flotation pilot testwork and process guarantees.
Grade riskPlant may not consistently achieve 5.5%–6% Li₂O concentrate.CriticalLocked-cycle testing and blend strategy.
Mineralogy riskOre may not liberate well or may contain mica/fines.HighMineralogy, liberation, and comminution study.
Impurity riskIron, mica, fluorine, or other impurities may affect sulphate plant.HighImpurity profiling and vendor feed acceptance tests.
Water riskFlotation and tailings need reliable water supply.HighWater balance and recycling system design.
Tailings riskLarge reject volume must be safely stored or dry-stacked.HighTailings management plan and EIA approval.
Power riskGrinding and flotation require reliable power.HighPower study and backup/captive options.
Capex overrunScope can expand if DMS + flotation + tailings are all required.HighFEED, vendor quotes, staged implementation.
Opex riskReagent, power, maintenance, and water costs may be higher.MediumPilot opex model and supplier quotations.
Downstream mismatchConcentrate may not fit sulphate plant calcination/leach requirements.CriticalTest concentrate directly in sulphate process route.

11. Decision Framework

Go / no-go screen for concentration plant investment.

Decision Scorecard

CriteriaWeightCurrent ScoreWeighted Score
Ore grade suitability15%609.0
Spodumene liberation15%558.3
Ability to achieve 6% concentrate20%5511.0
Recovery level20%5511.0
Impurity control10%606.0
Opex competitiveness10%656.5
Water / tailings / ESG5%603.0
Downstream sulphate fit5%502.5
Total100%57.3 / 100

Board Recommendation

57 / 100

Proceed to Pilot Beneficiation Testwork

Do not commit to full concentration plant EPC yet. Proceed with mineralogy, liberation study, DMS testing, flotation testing, dewatering tests, and downstream sulphate feed acceptance.

DecisionCondition
Proceed 6% concentrate, 70%+ recovery, stable impurity profile, acceptable opex, tailings solution approved.
Redesign 5.5%–6% concentrate possible but recovery, water, or opex is weak.
Reject / Pause Cannot produce 5.5% concentrate, recovery below 60%, or feed unsuitable for sulphate conversion.

12. Recommended Next Steps

PriorityActionReason
1Collect representative bulk ore sampleNeeded for reliable DMS/flotation and dewatering tests.
2Run mineralogy and liberation studyDetermines whether DMS, flotation, or combined route is best.
3Run DMS testworkChecks if low-cost coarse upgrading is possible.
4Run flotation locked-cycle testsConfirms concentrate grade, recovery, and stability.
5Test concentrate in sulphate processConfirms compatibility with calcination, acid roast, and leaching.
6Prepare preliminary process designConfirms equipment sizing and capex.
7Build full opex modelIncludes power, reagents, labour, maintenance, water, tailings, and lab.
8Update integrated project dashboardFeed actual concentrate cost and recovery into lithium sulphate ROI model.